Business Mathematics

51. The slack for an activity is equal to ______________

  1. LF-LS.
  2. EF-ES.
  3. LS-ES.
  4. None of the above.
Correct answer: (C)
LS-ES.

52. A dummy activity is used in the network diagram when ______________

  1. Two parallel activities have the same tail and head events.
  2. The chain of acitivities may have a common event yet he independent by themselves.
  3. Both a & b
  4. None of the above.
Correct answer: (C)
Both a & b

53. Activity –on-arrow (AOA) diagram is prefeered over Activity – on-node (AON) diagram because ______________

  1. AOA diagrams are simple to construct.
  2. AOA diagrams give a better sense of the flow of time throughout a project.
  3. AOA diagrams do not involve dummy activites
  4. ALL the above.
Correct answer: (B)
AOA diagrams give a better sense of the flow of time throughout a project.

54. Earliest finish time that an activity can be finished without ______________ of precedence requirements.

  1. Planning.
  2. Violation.
  3. Both a&b
  4. None of the above
Correct answer: (B)
Violation.

55. A small circle or rectangle that is known as ______________ serves as a junction point in the project network.

  1. Event.
  2. Node.
  3. Slack.
  4. Variables.
Correct answer: (B)
Node.

56. Project ______________ phase allocates resources to work packages.

  1. Planning.
  2. Scheduling.
  3. Controlling.
  4. Both b & c.
Correct answer: (A)
Planning.

57. The Objective function of Transportation problem is to ______________.

  1. maximize the total cost.
  2. minimize or maximize the total cost.
  3. minimize the total cost.
  4. total cost should be zero.
Correct answer: (C)
minimize the total cost.

58. In Least cost method the allocation is done by selecting ______________.

  1. upper left corner.
  2. upper right corner.
  3. middle cell in the transportation table.
  4. cell with the lowest cost.
Correct answer: (D)
cell with the lowest cost.

59. Purpose of MODI method is to get ______________.

  1. degenerate solution.
  2. non-degenerate solution.
  3. optimal.
  4. basic feasible solution.
Correct answer: (C)
optimal.

60. In transportation problem if total supply > total demand we add ______________.

  1. dummy row with cost 0.
  2. dummy column with cost 0.
  3. dummy row with cost 1.
  4. dummy column with cost 1.
Correct answer: (B)
dummy column with cost 0.