51. The slack for an activity is equal to ______________
- LF-LS.
- EF-ES.
- LS-ES.
- None of the above.
Correct answer: (C)
LS-ES.
52. A dummy activity is used in the network diagram when ______________
- Two parallel activities have the same tail and head events.
- The chain of acitivities may have a common event yet he independent by themselves.
- Both a & b
- None of the above.
Correct answer: (C)
Both a & b
53. Activity –on-arrow (AOA) diagram is prefeered over Activity – on-node (AON) diagram because ______________
- AOA diagrams are simple to construct.
- AOA diagrams give a better sense of the flow of time throughout a project.
- AOA diagrams do not involve dummy activites
- ALL the above.
Correct answer: (B)
AOA diagrams give a better sense of the flow of time throughout a project.
54. Earliest finish time that an activity can be finished without ______________ of precedence requirements.
- Planning.
- Violation.
- Both a&b
- None of the above
Correct answer: (B)
Violation.
55. A small circle or rectangle that is known as ______________ serves as a junction point in the project network.
- Event.
- Node.
- Slack.
- Variables.
Correct answer: (B)
Node.
56. Project ______________ phase allocates resources to work packages.
- Planning.
- Scheduling.
- Controlling.
- Both b & c.
Correct answer: (A)
Planning.
57. The Objective function of Transportation problem is to ______________.
- maximize the total cost.
- minimize or maximize the total cost.
- minimize the total cost.
- total cost should be zero.
Correct answer: (C)
minimize the total cost.
58. In Least cost method the allocation is done by selecting ______________.
- upper left corner.
- upper right corner.
- middle cell in the transportation table.
- cell with the lowest cost.
Correct answer: (D)
cell with the lowest cost.
59. Purpose of MODI method is to get ______________.
- degenerate solution.
- non-degenerate solution.
- optimal.
- basic feasible solution.
Correct answer: (C)
optimal.
60. In transportation problem if total supply > total demand we add ______________.
- dummy row with cost 0.
- dummy column with cost 0.
- dummy row with cost 1.
- dummy column with cost 1.
Correct answer: (B)
dummy column with cost 0.