Cost and Managerial Accounting
171. The budget relating to ______________ must be prepared first and the other budgets should be prepared in the light of that factor.
- Limiting factor
- materials
- labour
- production
Correct answer: (A)
Limiting factor
172. ______________ is the consolidated summary of the various functional budgets.
- Master Budget
- Sales budget
- Performance budget
- Cash Budget
Correct answer: (A)
Master Budget
173. Calendar Ratio=
- Number of actual working days in a period x 100
Number of working days in the budget period
- Actual hours worked x 100
Budgeted hours
- Standard hours for actual production x 100
Actual hours worked
- Standard hours for actual production x 100
Budgeted standard hours
Correct answer: (A)
Number of actual working days in a period x 100
Number of working days in the budget period
174. Cash Budget is a ______________ budget.
- Long term
- very long term
- short term
- very short term
Correct answer: (C)
short term
175. The budget that is prepared first of all is ______________
- Cash budget
- master budget
- budget for the key factor
- sales budget
Correct answer: (C)
budget for the key factor
176. Standard costing is more widely applied in ______________ industries.
- Process and engineering
- jobbing industries
- construction industry
- all of these
Correct answer: (A)
Process and engineering
177. Material price variance is the difference between standard and actual prices of materials used multiplied by ______________
- Actual quantity of materials used
- Budgeted quantity of materials used
- Standard quantity of materials used
- Either a or b
Correct answer: (A)
Actual quantity of materials used
178. Total Material cost variance=
- Standard cost of materials-actual cost of materials
- Budgeted cost of materials- actual cost of materials
- Standard cost of materials-budgeted cost of materials
- Actual cost of materials- budgeted cost of materials
Correct answer: (A)
Standard cost of materials-actual cost of materials
179. Total Labour cost variance=
- Standard cost of labour - actual cost of labour
- Standard rate(standard time for actual output-actual time worked)
- Standard rate (standard time for actual output- actual time paid for)
- Actual time taken (standard rate-actual rate)
Correct answer: (A)
Standard cost of labour - actual cost of labour
180. An unfavourable material usage arises because of:
- Price increase in raw materials
- Price decrease in raw mateials
- Less than anticipated normal wastage in the manufacturingprocess
- More than anticipated normal wastage in the manufacturing process
Correct answer: (D)
More than anticipated normal wastage in the manufacturing process