111. PERT emphasis on ______________.
- Time
- Activity
- a) and b)
- None of the above
Correct answer: (A)
Time
112. ______________ is an activity oriented diagram.
- CPM
- PERT
- Histogram
- None of the above
Correct answer: (A)
CPM
113. In a decision theory problem under complete uncertainty, which one of the following approaches will not be possible?
- Expected monetary value
- Maxmin
- Minimax
- Hurwicz
Correct answer: (A)
Expected monetary value
114. The equally likely decision criteria is also known as
- Bayes
- Laplace
- Minimax
- Hurwicz
Correct answer: (B)
Laplace
115. Which of the following might be viewed as an optimistic decision criterion?
- Hurwicz criterion
- Maximin
- Maximax
- Minimax
Correct answer: (C)
Maximax
116. While using Hurwicz criterion, the coefficient of realism
- Represents the degree of optimism
- Represents the degree of pessimism
- Is the probability of state of nature
- None of the above
Correct answer: (A)
Represents the degree of optimism
117. Operations research approach is
- Multi disciplinary
- Scientific
- Intuitive
- All of the above
Correct answer: (A)
Multi disciplinary
118. OR techniques helps to find ______________ solution
- Feasible
- Non feasible
- Optimal
- Non optimal
Correct answer: (C)
Optimal
119. An organization chart is an example of
- Iconic
- Mathematical
- Analogue
- None of the above
Correct answer: (C)
Analogue
120. Linear programming is a
- Constraint optimization technique
- Technique for economic allocation of limited resources.
- Mathematical technique
- all of the above
Correct answer: (D)
all of the above