Principles and Practices of Management
51. ______________ is the latest time by which an activity can be started without delaying the completion of the project.
- EST
- EFT
- LST
- LFT
Correct answer: (C)
LST
52. An activity which must be completed before one or more other activities start is known as ______________ activity.
- Dummy
- Predecessor
- Successor
- None of these
Correct answer: (B)
Predecessor
53. ______________ is the shortest possible time in which an activity can be delayed without delaying the project.
- Pessimistic time estimate
- Optimistic time estimate
- Most likely time estimate
- None of these
Correct answer: (B)
Optimistic time estimate
54. What decision-making condition must exist for the decision tree to be a valuable tool?
- Certainty
- Uncertainty
- Risk
- It does not matter, the tool is appropriate in all environments
Correct answer: (C)
Risk
55. The criteria of expected monetary value is used for making decisions under
- Certainty
- Uncertainty
- Risk
- all of the above
Correct answer: (D)
all of the above
56. The minimum expected opportunity loss is
- Equal to EVPI
- Minimum regret
- Equal to EMV
- Both (a) and (b)
Correct answer: (D)
Both (a) and (b)
57. The objective of network analysis is to
- Minimize total project duration
- Minimize total project cost
- Minimize production delays, interruption and conflicts
- All of the above
Correct answer: (A)
Minimize total project duration
58. Decision variables are
- Controllable
- Uncontrollable
- Parameters
- None of the above
Correct answer: (A)
Controllable
59. An optimization model
- Mathematically provides best decision
- Provides decision with limited context
- Helps in evaluating various alternatives constantly
- All of the above
Correct answer: (D)
All of the above
60. Modern scientific management research originated during ______________
- World war II
- World war I
- 1990
- 1993
Correct answer: (A)
World war II