131. __________________ calculates the timing and quantities of material orders needed to support the master schedule.
Sale and operations planning
Distribution requirements planning
Material requirements planning
Master production schedule
Correct answer: (C) Material requirements planning
132. Which of the following lot-sizing techniques is likely to prove the most complex to use?
Part period balancing (PPB)
The Wagner-Whitin algorithm
Economic order quantity (EOQ)
Lot-for-lot
Correct answer: (B) The Wagner-Whitin algorithm
133. __________________ is a time phased approach to managing the physical distribution environment with dependent demand logic.
Master production schedule
Distribution requirements planning
Sale and operations planning
Material requirements planning
Correct answer: (B) Distribution requirements planning
134. The list of quantities of components, ingredients, and materials required to produce a product is the
Bill-of-materials.
Engineering change notice.
Purchase order.
Master schedule.
Correct answer: (A) Bill-of-materials.
135. When a bill-of-materials is used in order to assign an artificial parent to a bill-of-materials, it is usually called a
Phantom bill-of-materials.
Planning bill-of-materials.
Modular bill-of-materials.
Pick list.
Correct answer: (B) Planning bill-of-materials.
136. __________________ can be seen as the amount of new inventory created by production.
Scheduled receipts
Gross requirements
Planning horizon
Available to promise
Correct answer: (D) Available to promise
137. A lot-sizing technique that generates exactly what was required to meet the plan is
The Wagner-Whitin algorithm.
Economic order quantity.
Lot-for-lot.
Part period balancing.
Correct answer: (C) Lot-for-lot.
138. The operations manager has several tools available to deal with MRP system nervousness. Those tools are
Pseudo bills and kits.
Time fences and pegging.
Buckets with back flush.
Net and gross requirements.
Correct answer: (B) Time fences and pegging.
139. __________________ is the amount of materials necessary to support production of the required output in the next higher level in the bill of materials.
Planning horizon
Available to promise
Net requirements
Gross requirements
Correct answer: (D) Gross requirements
140. Breaking up the order and running part of it ahead of schedule is known as