84. A master production schedule contains information about
Quantities and required delivery dates of all sub-assemblies
Quantities and required delivery dates of final products
Inventory on hand for each sub-assembly
Inventory on hand for each final product
Correct answer: (B) Quantities and required delivery dates of final products
85. Optimized production technology (OPT) is a computer-based technique and tool which helps to schedule production systems. Which of the following are not principles of OPT?
Capacity is "king"
Balance flow is what is required
Process batch should be variable
Bottlenecks govern throughput
Correct answer: (A) Capacity is "king"
86. MPS stands for:
Master Planning System
Master Production Schedule
Material Production Schedule
Material Planning System
Correct answer: (B) Master Production Schedule
87. A master production schedule contains information about
Quantities and required delivery dates of all sub-assemblies
Quantities and required delivery dates of final products
Inventory on hand for each sub-assembly
Inventory on hand for each final product
Correct answer: (B) Quantities and required delivery dates of final products
88. Dependent demand and independent demand items differ in that
For any product, all components are dependent-demand items
The need for independent-demand items is forecasted
The need for dependent-demand items is calculated
All of the above are true
Correct answer: (D) All of the above are true
89. A master production schedule specifies
The financial resources required for production
What component is to be made, and when
What product is to be made, and when
The labor hours required for production
Correct answer: (C) What product is to be made, and when
90. Closed Loop MRP means:
Actual inventory is counted regularly and adjustment made to the inventory records
Capacity and resource planning is included in the MRP logic
Unused materials are returned to stores and recorded back into the system
Actual sales are netted off the forecasts in the MPS
Correct answer: (B) Capacity and resource planning is included in the MRP logic